August 2010
The final school year for the merging schools has just begun- to see what is going on and how you could support the integration and preparation for the new school – please click here
October 2009- June 2010
Efforts were made to restart the SiTP parents forum and the group met several times over the school year. Attempts were made to engage with educational department and the architects and feed in our perspective on the proposed design of the school. The teachers
See notes from stakeholder meeting January 2010– Click Here
August 2009
The decision to proceed with new build was taken and the ground was broken in August 2009. Anticipated entry spring 2011.
29 April 2008
We are still waiting for a planning decision by committee to be taken and need your support! – Click here to go to the “how to get involved page”
23 April 2008
Hillhead Councillors met with parent and teachers representing all four schools. Concern about the apparent planning application delay remains high on the agenda.It was highlighted that we are unhappy with the lack of progress and that the status quo is wholly unsatisfactory. Awareness raising about the impact of the planning decision delay was made to the Councillors and they were asked to investigate this on the groups behalf
25th March 2008
Planning submission not yet reached committee, group voiced concerns about the impact of the apparent unusual delay. The group decided to invite Hillhead councillors to a meeting to voice our concerns.
February 2008
Planning submission not yet reached committee. Anticipating an early 2008 decision with a subsequent delayed entry date Spring 2010.